Karachi’s major water supply project, K-IV, has incurred expenditures of Rs. 86 billion to date, while approximately 40% of the project has been completed. An additional Rs. 70 billion will be required to complete the project.
During a meeting of the National Assembly Standing Committee on Water Resources, Federal Minister for Water Resources Moeen Wattoo informed the committee that a substantial amount had already been spent on the K-IV project and that further funding would be necessary to ensure its completion.
During the meeting, MQM-Pakistan Member of the National Assembly Ameen Ul Haque submitted a calling attention notice regarding delays in the K-IV project and questioned the project’s actual progress.
WAPDA Chairman Lieutenant General (Retd.) Muhammad Saeed briefed the committee that progress had previously been affected by a shortage of funds. However, the Government of Sindh has now released Rs. 7.7 billion, allowing work on the project to continue.
Committee members also expressed concern over Karachi’s ongoing water crisis and the influence of the water tanker mafia. Committee member Syed Waseem Aftab stated that residents are being forced to spend thousands of rupees to purchase water through private tankers.
Meanwhile, committee member Munawar Talpur questioned the sustainability of the K-IV project’s water source, noting that Keenjhar (Kalri) Lake has significantly dried up. He asked how Karachi’s future water supply could be ensured under these circumstances.